Installation Update - Jetty Piles
Precinct B - Exmouth Marina Village
Since the arrival of the Uni float Jack Up Barge in Early October steady progress has been made on the installation of the 68 jetty piles for Precinct B.
In Canal Arm 5 that runs parallel to Cobia Close and includes the Village Quays Marina, outer piles to all moorings have been completed, with the piles to be cut and the cross brace connection to inner piles installed.
As the pictures indicate, as of of Friday 29th October they are now working in the main canal installing piles to commercial moorings adjoining the footbridge.